Expansion Progress
December 4, 2025
By early December, the site is fully transformed from open ground into a prepared construction platform, ready to support the foundations and structural systems that will house the expanded LayerZero operations.
December 4, 2025
By early December, the site is fully transformed from open ground into a prepared construction platform, ready to support the foundations and structural systems that will house the expanded LayerZero operations.
November 19, 2025
Late-fall photos show a highly organized construction site, with major earthwork complete and the expansion area prepared for the next step in vertical construction.
November 17, 2025
The expansion footprint now has a clearly developed base, with ongoing work to ready the site for more advanced structural and utility installation.
November 12, 2025
Visible progress continues with more work on the building pad, underground infrastructure and staging areas for future phases of the expansion.
November 6, 2025
Construction progresses across the pad with additional groundwork and preparation for concrete, reinforcing the base for the upcoming structure.
November 4, 2025
Early foundational activity begins to appear on the site, as crews prepare the areas that will support the structural loads of the new facility.
October 29, 2025
With the pad largely established, the site is positioned to move into footing and foundation work, shifting focus from shaping the ground to building upward.
October 27, 2025
Grading and preparation are nearing completion across the main footprint. The site now clearly reflects the outline of the future building.
October 24, 2025
The day after the ceremony, work resumes at full speed. Equipment and crews continue transforming the freshly dedicated ground into the foundation for the new expansion.
October 23, 2025
LayerZero marks a major milestone with a formal groundbreaking ceremony at Philipp Parkway, celebrating the start of a long-term investment in increased manufacturing capacity and capability.
October 21, 2025
Final adjustments to the pad and surrounding grounds set the stage for the next phase of construction, aligning the site with the engineered design for drainage and load paths.
October 17, 2025
Site activity continues to build momentum. The expansion pad and surrounding areas are nearly ready to transition from earthwork into foundational construction.
October 15, 2025
A busy day on site: multiple work fronts operate in parallel to keep the project on schedule, from refining grade to preparing key areas for concrete and underground services.
October 14, 2025
The expansion zone shows more definition, with equipment, materials and grading focused on areas that will carry the highest structural loads.
October 13, 2025
Underground preparation advances as crews work across the pad to support future utilities, drainage and foundation layout for the expanded facility.
October 10, 2025
The construction footprint is now clearly established. Access paths, staging areas and the main pad are all taking shape as the site moves toward foundation work.
October 9, 2025
With grading well underway, crews continue to smooth, compact and fine-tune the expansion pad, ensuring a stable surface for structural work to follow.
October 8, 2025
Progress is visible along the full length of the future building. The site transitions from open field to a clearly defined construction zone ready for underground work.
October 6, 2025
Earthmoving accelerates across the site. Heavy equipment reshapes the expansion area, improving drainage and building up the pad where the new facility will stand.
October 3, 2025
Site preparation continues as crews refine elevations and shape the build area, creating a stable base for upcoming utilities and foundations.
October 1, 2025
Early site work begins to define the expansion footprint. Grading, layout and access routing prepare the ground for the first major construction steps.
September 29, 2025
Aerial views capture the existing Philipp Parkway campus and the open land that will become the new expansion – a clear before-shot of the site prior to heavy construction activity.